RENEWAL HSG SUBSTATION NO.1 (CANON THANG LONG)

The work of Renewal HSG substation No. 1 of Canon Thang Long factory was carried out by Thanh Cong contractor from April 30 to May 22, 2022 at Lot A1 North Thang Long Industrial Park, Kim Chung Commune, Dong Anh District, Hanoi.

1. Remove existing panels

 

2. Install and test new panels