Power off the 9# factory
Power off the outdoor 2500KVA kiosk substation
The project was started on September 5th, 2022 and officially completed and handed over to the investor on December 25th, 2022, this work is in phase I of Goertek Vina Factory project in Nghe An with investment capital up to 500 million USD. With the successful energizing of 9# factory and substation, it has contributed to catching up with the project schedule, completing phase I and putting it into operation and production.