Since receiving the notice of winning the bid, Thanh Cong has planned maintenance and personnel, established a project committee to meet with the Investor on the maintenance plan for the power system of the plant. With a large scale of 2 factories and only done in one day, the volume of work is very large, but with the 4th year experience, Thanh Cong is confident that it can complete the work on time and with the required quality.
This year, maintenance work still takes place on the first Sunday of October, October 2. Due to the influence of Typhoon Naru, there was light rain in the early morning but gradually became more beautiful, and in the afternoon, this is also a lucky point for the maintenance work to take place more smoothly.
Right from the early morning, the temporary electric team was present at the factory to perform temporary electrical connection work in preparation for maintenance. At 6:30 am, all 350 employees including engineers were present at Kyocera to participate in safety meetings and disseminate work.
After the safety meeting, the teams were assigned to the area in charge and started the maintenance work according to the attached detailed photo report.
Although the work is still difficult and strenuous, the time to work in the hospital is until 3 am the next day, but Thanh Cong's team of engineers and staff are still steadfast, working enthusiastically to ensure the quality goals and to The factory can go back to work the next day.