After receiving an order from Canon, Thanh Cong rushed to place an order at the request of the investor with the supplier Daikin and performed preparatory work before the goods arrived. Transporting materials, installing backup wind pipes for 2 AHU
Moved AHU to factory on April 14, 2022.
Dismantle the old AHU and fan
Install new fan, motor AHU
Finishing and testing AHU 203
Replace control cabinet and new solenoid valve, connect new electrical panel and connect to BMS system
Installing AHU 202
By 11/05/2022 all work was completed, Thanh Cong handover to the factory.