After receiving an order from Canon, Thanh Cong rushed to place an order at the request of the investor with the supplier Daikin and performed preparatory work before the goods arrived. Transporting materials, installing backup wind pipes for 2 AHU
![]() | ![]() |
Moved AHU to factory on April 14, 2022.
![]() | ![]() |
Dismantle the old AHU and fan
![]() | ![]() |
Install new fan, motor AHU
![]() | ![]() |
Finishing and testing AHU 203
![]() | ![]() |
Replace control cabinet and new solenoid valve, connect new electrical panel and connect to BMS system
![]() | ![]() |
Installing AHU 202
![]() | ![]() |
By 11/05/2022 all work was completed, Thanh Cong handover to the factory.
![]() | ![]() |