At 7:00 am on April 30th, all employees and engineers in charge of maintenance gathered at Kyocera factory at Lot B1 Thang Long Industrial Park II.
![]() | ![]() |
After focusing on implementing the work, maintenance personnel are divided into 10 respective groups, in charge of assigned areas.
![]() | ![]() |
![]() | ![]() |
Under the supervision of factory technicians, Thanh Cong conducts maintenance work and reports errors, problems, and work status to the technicians.
![]() | ![]() |
At 11 pm on the same day, all maintenance areas were turned on, factory technicians made a final check and confirmed the work was completed.
![]() | ![]() |
Although working on a public holiday, the staffs of Thanh Cong ME Construction Joint Stock Company are still actively participating in maintenance work, putting quality goals on the top, performing the entire job in a timely manner with the most careful, safe and professional way at the request of the Investor.