IMPROVE THE WORKING ENVIRONMENT FOR TVN3 KITCHEN

IMPROVE THE WORKING ENVIRONMENT FOR TVN3 KITCHEN

Project name: Improving the working environment of TVN3's kitchen area Investor: TOTO Vietnam Co., Ltd Location: Lot M7, M8, N3 and RE8 Thang Long Industrial Park II, Phung Chi Kien Ward, My Hao Town, Hung Yen, Vietnam. Scope of work: Construction and renovation of kitchen TVN3 Construction time: 2023
Commencement to increase capacity of 220kV Dong Ha substation

Commencement to increase capacity of 220kV Dong Ha substation

On November 22nd, 2022, in Trieu Phong district, Quang Tri province, the National Power Transmission Corporation (EVNNPT) cooperated with the contractor of the Joint Venture Thanh Cong ME Construction Joint Stock Company and the PC1 group-My Dinh organized the groundbreaking of the project "Upgrading capacity of 220kV Dong Ha substation from 2x125 MVA to (125+250) MVA".
ELECTRICITY PROJECT PAGE I-1 GOERTEK NGHE AN FACTORY

ELECTRICITY PROJECT PAGE I-1 GOERTEK NGHE AN FACTORY

Investor: Goertek Precision Industry Co., Ltd Location: WHA Industrial Park, Southeast Economic Zone, Nghe An Scope of construction: General contractor for design and construction of electrical works - The 24kV power supply outside the house: circuit breakers, power poles, electric wells... - The power center part: output, input, capacitor... - Workshop part: output, input, capacitor... Construction period: 2021-2022 Some project pictures:
CANON FACTORY PROJECT IN TIEN SON, QUE VO, THANG LONG IP

CANON FACTORY PROJECT IN TIEN SON, QUE VO, THANG LONG IP

Investor: Canon Vietnam Co., Ltd Location: Tien Son Industrial Park, Que Vo Industrial Park, Thang Long Industrial Park I Scope of work: Construction of mechanical and electrical works - Upgrade the function of building monitoring system - Power supply system, power supply for production and mechanical equipment - Telephone and data systems - Access control and security system - Fire alarm system, grounding system and lightning protection - Supply and install electrical cabinets, transformers - Broadcasting system - Air conditioning system - Waste water treatment system... Construction period: 2019-2022 Some project pictures:
B. BRAUN MEDICAL EQUIPMENT FACTORY- EXPANDING PROJECT (Phase 3)

B. BRAUN MEDICAL EQUIPMENT FACTORY- EXPANDING PROJECT (Phase 3)

Investor: B. Braun Vietnam Co., Ltd Location: Thanh Oai Industrial Park, Hanoi Scope of work: Electrical and Compressed air work - Building monitoring system - Energy management system - Power supply system, power supply for production and mechanical equipment - Telephone and data systems - Access control and security system - Fire alarm system, grounding system and lightning protection - Electrical work to reconstruct and supply the power system outside the building - Compressed air Construction time: 2022